Projects dont come more controversial than the Canal de Nicaragua, a 173-mile shipping channel that Chinese corporation Hong Kong Nicaragua Canal Development Investment Company (HKND) hopes to slice through Central America. When 勛圖窪蹋 reporter Brian Kevin traveled to Brito, the canals western terminus, last year, he heard a common concern: HKND was embarking on construction before researching the projects environmental impacts. (T)hey dont want to give us the results of the studies that theyre supposedly doing, one scientist complained.
HKND was originally scheduled to break ground in early 2014, but has pushed that back to to conduct more studies. Last week, the company publicly released its long-awaited (ESIA), which HKND had hired the London-based consultancy Environmental Resource Management (ERM) to complete. The report had been dogged by accusations of inadequacy since experts first reviewed a draft back in March, with one biologist one of the most mismanaged environmental reviews I have ever read.
Though the public version has filled in some of the blanks, its hardly a reassuring document: It identifies some vital unanswered questions, most notably the risk of seismic damage and whether theres actually enough water during dry season to sustain the channel. And while the report ultimately advocates neither for nor against the canal, it confirms some of the publics worst fears about the projects immense ecological and social footprint.
Start with the harm to Lake Nicaragua, the 3,000-square-mile body of water through which the canal will pass. The freshwater lake is home to a panoply of fish, including tarpon, sawfish, and sharks, and its wetlands support more than 300 bird species, from the Pygmy Kingfisher to the Muscovy Duck. Digging the channel deep enough for massive ships to pass between the Atlantic and Pacific Oceans would require dredging 5 billion cubic meters of sediment from the lake floor, a procedure that the report acknowledges could stir up pollutants, and resurface other chemicals and nutrients, possibly causing organisms to require more oxygen to survive. Construction could also harm nearly 1,000 acres of the San Miguelito wetlands along the lakes eastern shore.
The effects on wildlife extend beyond the lakes borders: Altogether, the canal would disturb more than 200,000 acres of critical wildlife habitat, from jaguar-filled forests to sea turtle nesting beaches. The canal would be an obstacle for movement for all but the most mobile wildlife species色 says the report, creating barrier effects that would result in the disruption of wildlife movement and reduced gene flow north and south of the canal.
Human communities, too, will almost certainly be harmed. Some 30,000 people living within the project area would face physical or economic displacement, yet HKND hasnt yet discussed the terms of land acquisition or resettlement with locals, the report states. No wonder, then, that while polls suggest that a majority of Nicaraguans at least partly support the project, its strongly opposed by affected communities. Consultation and information sharing with people potentially subject to involuntary resettlement has been especially inadequate, the assessment concedes.
Whats going to happen to the communities in the crosshairs, and what are the impacts to Lake Nicaragua as a result of dredging? says John Myers, senior Latin American program manager for 勛圖窪蹋. Those are still the two biggest issues, in my view.
Though it emphasizes the potential for harm, the report concludes that the project does offer potential benefits to the environment and people of Nicaragua, Latin Americas second poorest countrybut only if makes good on its promised mitigation work. The company has agreed to work with the government to complete measures like designating marine protected areas and establishing investment programs for affected communities. But the report warns that HKND may struggle to mitigate the damage, as the company, which is controlled by telecom executive Wang Jing, lacks experience with projects of the canals magnitude.
Furthermore, the slumping Chinese stock market has reduced Wangs fortune by since June, casting doubt on his ability to finance the canal. The uncertain financing and timeline raises an alarming possibility: That HKND will begin construction but fail to complete it. If that happens, warns the assessment, Nicaragua may be worse off than doing nothing.
That warning squares with the concerns of many Nicaraguans. Its going to be the good, the bad and the ugly, says Alvaro Molina, who owns a hotel on Ometepe, a volcanic island in Lake Nicaragua. While Molina fears pollution in the lake and catastrophic deforestation, he also believes the canal could create educational opportunities for locals, many of whom, he says, remain illiterate. But if the canal goes through and better education doesnt happen, then well end up just as bad or worse than before.